The Bureau of Land Management (BLM) Pinedale Field Office (PFO) is seeking public input on the environmental assessment (EA) for the proposed Anticline Electrification Phase I Project.
Phase I construction consists of three parts:
Approximately 23.5 miles of 25 kilovolt (kV) distribution line on wood poles beginning just north of Paradise Road and proceeding south and east along the backbone of the Anticline towards Highway 191.
Approximately five miles of 69 kV transmission line from Highway 351 north to the Boulder South County Road 23-106 and a substation south of Highway 351 and west of the North Jonah Road.
A 10-mile reroute of the authorized Paradise 230 kV transmission line. Currently, this line is authorized to parallel Highway 191 to Highway 351 then follow Highway 351 to the Paradise Road. The transmission line reroute would go from Highway 191 west to the Falcon Compressor area and then north along the backbone of the Anticline to Highway 351 parallel to the above mentioned 25 kV distribution line.
Construction of the 25 kV distribution line is anticipated to begin in the late summer or early fall of 2012; the 69 kV and 230 kV transmission lines would be constructed as needed.
Mail or deliver written comments to the PFO, 1625 W. Pine St., P.O. Box 768, Pinedale, WY 82941; fax to 307-367-5329; or email to bwadswor@blm.gov with “Electrification Phase I” in the subject line. Comments must be received by 4:30 p.m., Wednesday, June 20.
Phase I construction consists of three parts:
Approximately 23.5 miles of 25 kilovolt (kV) distribution line on wood poles beginning just north of Paradise Road and proceeding south and east along the backbone of the Anticline towards Highway 191.
Approximately five miles of 69 kV transmission line from Highway 351 north to the Boulder South County Road 23-106 and a substation south of Highway 351 and west of the North Jonah Road.
A 10-mile reroute of the authorized Paradise 230 kV transmission line. Currently, this line is authorized to parallel Highway 191 to Highway 351 then follow Highway 351 to the Paradise Road. The transmission line reroute would go from Highway 191 west to the Falcon Compressor area and then north along the backbone of the Anticline to Highway 351 parallel to the above mentioned 25 kV distribution line.
Construction of the 25 kV distribution line is anticipated to begin in the late summer or early fall of 2012; the 69 kV and 230 kV transmission lines would be constructed as needed.
Mail or deliver written comments to the PFO, 1625 W. Pine St., P.O. Box 768, Pinedale, WY 82941; fax to 307-367-5329; or email to bwadswor@blm.gov with “Electrification Phase I” in the subject line. Comments must be received by 4:30 p.m., Wednesday, June 20.